Taxpayers were stung an extra $16.5 million for a Big Build level crossing removal project after former premier Jacinta Allan ordered builders to change their preferred approach and keep Frankston line express trains running ahead of the 2022 state election.

Planned track closures were instead pushed back to December that year – just days after voters went to the polls.

Documents obtained under freedom-of-information laws show that Allan, then the transport infrastructure minister, directed contractors on the Glen Huntly station level crossing removal project to rewrite their construction schedule to prevent express train cancellations from…